Buildings and Facilities25HD0139

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) -MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN ROQUE, CITY OF TALISAY, CEBU

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) -MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN ROQUE, CITY OF TALISAY, CEBU is a DPWH-tracked public work in Cebu 1st DEO, Region VII. Reported contract value: ₱9,894,888.88. Status: Past target date (DPWH On-Going). Contractor on record: APURA CONST CORP 54043. Figures trace to dpwh.

Cebu 1st DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Naga River (Upstream), Tinaan, City of Naga, Cebu
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-25-0008820

₱2,391,464,863.61 · FY2025

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 54043

9 projects · ₱112.2M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, TALISAY CENTRAL SCHOOL, BRGY. POBLACION, TALISAY CEBU

Cebu 1st DEO, Region VII

2024₱29.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, EXTENSION OF MUNICIPAL BUILDING, BRGY. POBLACION, SIBONGA, CEBU

Cebu 1st DEO, Region VII

2023₱14.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INSFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. EAST POBLACION, NAGA CITY, CEBU

Cebu 1st DEO, Region VII

2023₱14.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI- PURPOSE BUILDING (COVERED COURT), BRGY. PITALO, SAN FERNANDO, CEBU

Cebu 1st DEO, Region VII

2025₱14.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY ILIHAN, TABOGON, CEBU

Cebu 4th DEO, Region VII

2025₱14.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF SCHOOL BUILDING, CITY OF BOGO SCIENCE AND ARTS ACADEMY, BARANGAY COGON, BOGO CITY, CEBU

Cebu 4th DEO, Region VII

2023₱9.9M
Reported complete (DPWH)
View all 9 projects →

4. Implementation

Contract Amount

₱9,894,888.88

Progress

Past target date (DPWH On-Going)

Start Date

March 18, 2025

Target End

September 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.