Buildings and Facilities23HD0071

CONSTRUCTION OF SCHOOL BUILDING, CITY OF BOGO SCIENCE AND ARTS ACADEMY, BARANGAY COGON, BOGO CITY, CEBU

CONSTRUCTION OF SCHOOL BUILDING, CITY OF BOGO SCIENCE AND ARTS ACADEMY, BARANGAY COGON, BOGO CITY, CEBU is a DPWH-tracked public work in Cebu 4th DEO, Region VII. Reported contract value: ₱9,900,000.00. Status: Reported complete (DPWH). Contractor on record: APURA CONST CORP. Figures trace to dpwh.

Cebu 4th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Cogon, Cebu City, Cebu
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cebu 4th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

9 projects · ₱112.2M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, TALISAY CENTRAL SCHOOL, BRGY. POBLACION, TALISAY CEBU

Cebu 1st DEO, Region VII

2024₱29.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, EXTENSION OF MUNICIPAL BUILDING, BRGY. POBLACION, SIBONGA, CEBU

Cebu 1st DEO, Region VII

2023₱14.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INSFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. EAST POBLACION, NAGA CITY, CEBU

Cebu 1st DEO, Region VII

2023₱14.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI- PURPOSE BUILDING (COVERED COURT), BRGY. PITALO, SAN FERNANDO, CEBU

Cebu 1st DEO, Region VII

2025₱14.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY ILIHAN, TABOGON, CEBU

Cebu 4th DEO, Region VII

2025₱14.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) -MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN ROQUE, CITY OF TALISAY, CEBU

Cebu 1st DEO, Region VII

2025₱9.9M
Past target date (DPWH On-Going)
View all 9 projects →

4. Implementation

Contract Amount

₱9,900,000.00

Progress

Reported complete (DPWH)

Start Date

June 7, 2023

Target End

October 4, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.