Rehabilitation / Major Repair of Flood Control Structure23KH0010

Rehabilitation of Iponan Flood Control Works, Revetment (Iponan Bridge I & II - Iponan Bridge III), along Iponan River, Bulua Side, Sta. 1+088.00 - Sta. 1+441.00 with exception, Brgy. Iponan, Cagayan de Oro City

Rehabilitation of Iponan Flood Control Works, Revetment (Iponan Bridge I & II - Iponan Bridge III), along Iponan River, Bulua Side, Sta. 1+088.00 - Sta. 1+441.00 with exception, Brgy. Iponan, Cagayan de Oro City is a DPWH-tracked public work in CAGAYAN DE ORO CITY (CAPITAL) (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X. Reported contract value: ₱24,500,000.00. Status: Reported complete (DPWH). Contractor on record: ESR CONST AND DEVELOPMENT CORP FORMERLY: ESR CONST & SUPPLIES. Figures trace to sumbong.

CAGAYAN DE ORO CITY (CAPITAL) (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Iponan Flood Control Works, Revetment (Iponan Bridge I & II - Iponan Bridge III), along Iponan River, Bulua Side, Sta. 1+088.00 - Sta. 1+441.00 with exception, Brgy. Iponan, Cagayan de Oro City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-23-0024352

₱30,827,000.00 · FY2023

Released to 0000000 Capiz State - University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱24,500,000.00

Progress

Reported complete (DPWH)

Start Date

January 30, 2023

Target End

September 23, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.