Construction of Flood Mitigation Structure24GM0016

Construction of Flood Mitigation Structure along Ilog-Bungol River (Downstream of Approach A of Malabong Br.), Ilog, Negros Occidental

Construction of Flood Mitigation Structure along Ilog-Bungol River (Downstream of Approach A of Malabong Br.), Ilog, Negros Occidental is a DPWH-tracked public work in ILOG (NEGROS OCCIDENTAL), NEGROS OCCIDENTAL, Region VI. Reported contract value: ₱110,098,780.00. Status: Reported complete (DPWH). Contractor on record: M K U CONST AND SUPPLY. Figures trace to sumbong.

ILOG (NEGROS OCCIDENTAL), NEGROS OCCIDENTAL, Region VI
Region: Region VI

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2024 · ₱50,000

    Probable match · score 0.90

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-BMB-D-24-0014212 · ₱2,977,141 · release to the district office, not itemized per project

    Possible match · score 0.66

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 24GM0016 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2024-01-04 → 2024-12-04

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Negros Occidental

Based on the coordinates published with the DPWH record and NOAH file NegrosOccidental.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: Construction of Flood Mitigation Structure along Ilog-Bungol River (Downstream of Approach A of Malabong Br.), Ilog, Negros Occidental

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Patic Creek ( Phase 4 ) , Barangay Patic, Pulupandan, Negros Occidental
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-D-24-0014212

₱2,977,141.00 · FY2024

Released to Regional Office - I (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0009998

₱1,848,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0016817

₱748,427.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0010001

₱171,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

77 projects · ₱1.0B total · 1 flags

4. Implementation

Contract Amount

₱110,098,780.00

Progress

Reported complete (DPWH)

Start Date

February 12, 2024

Target End

October 5, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Negros Island Region (NIR)Negros OccidentalIlogAndulauan
Storms whose wind field reached it
Penha 2026Koto 2025Kalmaegi 2025
Hazard exposure
Flood (100-yr rain)Storm surgeDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.