Construction of Flood Mitigation Structure22BB0012

Construction of Flood Control at Nangalinan, Baggao, Cagayan

Construction of Flood Control at Nangalinan, Baggao, Cagayan is a DPWH-tracked public work in BAGGAO (CAGAYAN), CAGAYAN, Region II. Reported contract value: ₱29,385,000.00. Status: Reported complete (DPWH). Contractor on record: APS CONST. Figures trace to sumbong.

BAGGAO (CAGAYAN), CAGAYAN, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control at Nangalinan, Baggao, Cagayan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-22-0007797

₱107,065,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002959

₱446,985,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-22-0003637

₱1,122,803.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-22-0003638

₱100,632.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

143 projects · ₱1.5B total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - BRIDGE - REPLACEMENT OF PERMANENT WEAK BRIDGES - REPLACEMENT OF WEAK BRIDGE - NADDUNGAN BR. 1 (B02132LZ) ALONG JCT. MAGAPIT CAPISSAYAN ROAD, GATTARAN, CAGAYAN

Cagayan 1st DEO, Region II

2025₱70.2M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - CONSTRUCTION OF BY - PASS AND DIVERSION ROADS - CONSTRUCTION OF CONCRETE ROAD - GATTARAN DIVERSION ROAD (PACKAGE I), CAGAYAN, GATTARAN, CAGAYAN

Cagayan 1st DEO, Region II

2022₱57.3M
Reported complete (DPWH)
No sat.

OO1 - ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - ROAD WIDENING - DUGO-SN VICENTE RD (MISSION-STA ANA SECT) - K0632 + 324.48 - K0634 + 689, STA. ANA, CAGAYAN

Cagayan 1st DEO, Region II

2025₱49.0M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCL. LOCAL PROJECTS-CONSTRUCTION OF CONCRETE ROAD-CONST. OF PATUNUNGAN-PANANACPAN ROAD, BARANGAY PATUNUNGAN, SANTA ANA, CAGAYAN

Cagayan 1st DEO, Region II

2021₱39.0M
Reported complete (DPWH)
No sat.

Construction of Flood Control Structure along Cagayan River, Dugo, Camalaniugan, Cagayan

CAMALANIUGAN (CAGAYAN), CAGAYAN, Region II

2023₱35.3M
Reported complete (DPWH)
No sat.

Construction of Flood Control Structure along Cagayan River, Bulala, Camalaniugan, Cagayan

CAMALANIUGAN (CAGAYAN), CAGAYAN, Region II

2023₱35.3M
Reported complete (DPWH)
View all 143 projects →

4. Implementation

Contract Amount

₱29,385,000.00

Progress

Reported complete (DPWH)

Start Date

February 2, 2022

Target End

October 20, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.