Construction of Flood Mitigation Structure24E00133

Construction of Aborlan River Waterway, (Downstream Leftside) Aborlan, Palawan

Construction of Aborlan River Waterway, (Downstream Leftside) Aborlan, Palawan is a DPWH-tracked public work in ABORLAN (PALAWAN), PALAWAN, Region IV-B. Reported contract value: ₱154,398,410.80. Status: Reported complete (DPWH). Contractor on record: YURICH BUILDERS AND CONST SUPPLY INC. Figures trace to sumbong.

ABORLAN (PALAWAN), PALAWAN, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱18,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Apurawan River Upstream ( L / S ) , Aborlan, Palawan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXII-24-0010585

₱9,500.00 · FY2024

Released to Lika National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008381

₱1,681,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0003151

₱464,327.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008395

₱155,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

158 projects · ₱6.0B total · 1 flags

4. Implementation

Contract Amount

₱154,398,410.80

Progress

Reported complete (DPWH)

Start Date

March 2, 2024

Target End

January 11, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.