Construction of Flood Mitigation Structure23P00020

Construction of Barren River (Downstream) Flood Control within Chico River Basin, Sta. 37+995 - Sta. 39+300 (R/S), Conner, Apayao

Construction of Barren River (Downstream) Flood Control within Chico River Basin, Sta. 37+995 - Sta. 39+300 (R/S), Conner, Apayao is a DPWH-tracked public work in CONNER (APAYAO), APAYAO, Cordillera Administrative Region. Reported contract value: ₱115,800,000.00. Status: Reported complete (DPWH). Contractor on record: JOMARCANN GEN CONST / RODEKOM GEN CONST AND ENT. Figures trace to sumbong.

CONNER (APAYAO), APAYAO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Barren River (Downstream) Flood Control along Chico River Basin, Sta. 37 + 414 - Sta. 37 + 664 (R/S), Barangay Paddaoan, Conner, Apayao
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-23-0021169

₱646,190.00 · FY2023

Released to Bagamanoc Rural Development High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱115.8M total · 0 flags

4. Implementation

Contract Amount

₱115,800,000.00

Progress

Reported complete (DPWH)

Start Date

April 12, 2023

Target End

February 29, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.