Construction of Flood Mitigation Structure23HK0063

Construction of Tamogong River Control, Bais City, Negros Oriental

Construction of Tamogong River Control, Bais City, Negros Oriental is a DPWH-tracked public work in BAIS CITY (NEGROS ORIENTAL), NEGROS ORIENTAL, Region VII. Reported contract value: ₱96,500,000.00. Status: Reported complete (DPWH). Contractor on record: PHILSOUTH BUILDERS INC FORMERLY:PHILSOUTH BUILDERS. Figures trace to sumbong.

BAIS CITY (NEGROS ORIENTAL), NEGROS ORIENTAL, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bateria River (Upstream), Guihulngan City, Negros Oriental
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-23-0027182

₱1,099,005.00 · FY2023

Released to Philippine Merchant Marine Academy (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

276 projects · ₱11.8B total · 28 flags

Other projects by this contractor

No sat.

CSSP, SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, REHAB./ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS ALONG BAIS-KABANKALAN RD - K0070+000 - K0071+000, K0075 + 459 - K0076 + 598, K0087+000-K0088+054, K0090+00-K0091+000,

Region VII, Region VII

2024₱253.4M
Past target date (DPWH On-Going)
No sat.

IMPROVEMENT/WIDENING OF DUMAGUETE SOUTH RD INCLUDING RROW (S00275NR), K0011+360 - K0012+277.46; K0012+310 - K0016+340, BACONG, NEGROS ORIENTAL

Negros Oriental 3rd DEO, Negros Island Region

2017₱152.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF SEAWALL, BARANGAY NORTH POBLACION, JIMALALUD, NEGROS ORIENTAL

Negros Island Region, Negros Island Region

2025₱149.6M
Past target date (DPWH On-Going)
No sat.

IMPROVEMENT/ WIDENING OF METRO DUMAGUETE DIVERSION ROAD INCL. RROW, DUMAGUETE CITY, NEGROS ORIENTAL

Negros Oriental 2nd DEO, Negros Island Region

2017₱146.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS DUMAGUETE NORTH RD-K0025+000-K0025+223, K0025+238-K0026+000, K0027+598-K0028+740, NEGROS ORIENTAL PROVINCE

Region VII, Region VII

2020₱144.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM: PREVENTIVE MAINTENANCE : SECONDARY ROADS: STA. CATALINA-PAMPLONA-TANJAY CITY - K0067 + 500 - K0072 + 000, STA. CATALINA, NEGROS ORIENTAL

Negros Oriental 3rd DEO, Negros Island Region

2025₱144.6M
Past target date (DPWH On-Going)
View all 276 projects →

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Reported complete (DPWH)

Start Date

March 10, 2023

Target End

February 12, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.