Buildings and Facilities24HE0126

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) MULTI-PURPOSE BUILDING, BARANGAY TUBOD, SAN FERNANDO, CEBU

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) MULTI-PURPOSE BUILDING, BARANGAY TUBOD, SAN FERNANDO, CEBU is a DPWH-tracked public work in Cebu 1st DEO, Region VII. Reported contract value: ₱1,978,888.88. Status: Reported complete (DPWH). Contractor on record: APURA CONST CORP. Figures trace to dpwh.

Cebu 1st DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage System at Barangay, Gawaygaway, San Remigio, Cebu
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-24-0011737

₱57,620,507.20 · FY2024

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

9 projects · ₱112.2M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, TALISAY CENTRAL SCHOOL, BRGY. POBLACION, TALISAY CEBU

Cebu 1st DEO, Region VII

2024₱29.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, EXTENSION OF MUNICIPAL BUILDING, BRGY. POBLACION, SIBONGA, CEBU

Cebu 1st DEO, Region VII

2023₱14.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INSFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. EAST POBLACION, NAGA CITY, CEBU

Cebu 1st DEO, Region VII

2023₱14.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI- PURPOSE BUILDING (COVERED COURT), BRGY. PITALO, SAN FERNANDO, CEBU

Cebu 1st DEO, Region VII

2025₱14.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY ILIHAN, TABOGON, CEBU

Cebu 4th DEO, Region VII

2025₱14.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF SCHOOL BUILDING, CITY OF BOGO SCIENCE AND ARTS ACADEMY, BARANGAY COGON, BOGO CITY, CEBU

Cebu 4th DEO, Region VII

2023₱9.9M
Reported complete (DPWH)
View all 9 projects →

4. Implementation

Contract Amount

₱1,978,888.88

Progress

Reported complete (DPWH)

Start Date

June 3, 2024

Target End

October 1, 2024

5. Audit