Buildings and Facilities19H00030

CLUSTER: CONSTRUCTION/REHABILITATION OF ACCESSIBILITY FACILITIES FOR PHYSICALLY CHALLENGED PERSON AT 1) REGIONAL OFFICE 7, SOUTH ROAD PROPERTIES, 2) CEBU 1ST DEO, BRGY. POBLACION, MEDELLIN, CEBU, 3) CEBU 5TH DEO, BRGY. GUINSAY, DANAO CITY, CEBU, 4) BOHOL

CLUSTER: CONSTRUCTION/REHABILITATION OF ACCESSIBILITY FACILITIES FOR PHYSICALLY CHALLENGED PERSON AT 1) REGIONAL OFFICE 7, SOUTH ROAD PROPERTIES, 2) CEBU 1ST DEO, BRGY. POBLACION, MEDELLIN, CEBU, 3) CEBU 5TH DEO, BRGY. GUINSAY, DANAO CITY, CEBU, 4) BOHOL is a DPWH-tracked public work in Region VII, Region VII. Reported contract value: ₱22,955,271.93. Status: Reported complete (DPWH). Contractor on record: JCJD CONST. Figures trace to dpwh.

Region VII, Region VII
Region: Region VII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

13 projects · ₱48.2M total · 0 flags

Other projects by this contractor

No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BRGY. SAWANG CALERO, CEBU CITY

Cebu City DEO, Region VII

2020₱4.9M
Reported complete (DPWH)
No sat.

CLUSTER PROJECT: CONSTRUCTION OF RAIN WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS-RAIN WATER COLLECTORS IN PUBLIC FACILITIES-19 UNITS, 1. 1 UNIT-CITY CENTRAL ELEMENTARY SCHOOL, CEBU CITY, 2. 2 UNITS-SAN ROQUE ELEMENTARY SCHOOL, TALISAY CITY

Region VII, Region VII

2020₱4.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REPAIR/REHAB/COMPLETION/IMPROVEMENT OF MULTI-PURPOSE BUILDING BARANGAY TAPUL, TALISAY CITY, CEBU

Cebu 1st DEO, Region VII

2019₱4.0M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BRGY. CALAMBA, CEBU CITY

Cebu City DEO, Region VII

2020₱2.9M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS - CONCRETING OF ROAD, BRGY. HIPODROMO, CEBU CITY

Cebu City DEO, Region VII

2020₱2.0M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURE - MULTI PURPOSE / FACILITIES - CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BRGY. MABINI, CEBU CITY

Cebu City DEO, Region VII

2020₱1.5M
Reported complete (DPWH)
View all 13 projects →

4. Implementation

Contract Amount

₱22,955,271.93

Progress

Reported complete (DPWH)

Start Date

January 13, 2020

Target End

February 4, 2021

5. Audit