Buildings and Facilities19HE0080

CONSTRUCTION/REPAIR/REHAB/COMPLETION/IMPROVEMENT OF MULTI-PURPOSE BUILDING BARANGAY TAPUL, TALISAY CITY, CEBU

CONSTRUCTION/REPAIR/REHAB/COMPLETION/IMPROVEMENT OF MULTI-PURPOSE BUILDING BARANGAY TAPUL, TALISAY CITY, CEBU is a DPWH-tracked public work in Cebu 1st DEO, Region VII. Reported contract value: ₱3,960,000.00. Status: Reported complete (DPWH). Contractor on record: JCJD CONST. Figures trace to dpwh.

Cebu 1st DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXII-19-0017947

₱170,249.00 · FY2019

Released to Pampanga 1st District Engineering Offi Division of Koronadal City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

13 projects · ₱48.2M total · 0 flags

Other projects by this contractor

No sat.

CLUSTER: CONSTRUCTION/REHABILITATION OF ACCESSIBILITY FACILITIES FOR PHYSICALLY CHALLENGED PERSON AT 1) REGIONAL OFFICE 7, SOUTH ROAD PROPERTIES, 2) CEBU 1ST DEO, BRGY. POBLACION, MEDELLIN, CEBU, 3) CEBU 5TH DEO, BRGY. GUINSAY, DANAO CITY, CEBU, 4) BOHOL

Region VII, Region VII

2019₱23.0M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BRGY. SAWANG CALERO, CEBU CITY

Cebu City DEO, Region VII

2020₱4.9M
Reported complete (DPWH)
No sat.

CLUSTER PROJECT: CONSTRUCTION OF RAIN WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS-RAIN WATER COLLECTORS IN PUBLIC FACILITIES-19 UNITS, 1. 1 UNIT-CITY CENTRAL ELEMENTARY SCHOOL, CEBU CITY, 2. 2 UNITS-SAN ROQUE ELEMENTARY SCHOOL, TALISAY CITY

Region VII, Region VII

2020₱4.1M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BRGY. CALAMBA, CEBU CITY

Cebu City DEO, Region VII

2020₱2.9M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS - CONCRETING OF ROAD, BRGY. HIPODROMO, CEBU CITY

Cebu City DEO, Region VII

2020₱2.0M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURE - MULTI PURPOSE / FACILITIES - CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BRGY. MABINI, CEBU CITY

Cebu City DEO, Region VII

2020₱1.5M
Reported complete (DPWH)
View all 13 projects →

4. Implementation

Contract Amount

₱3,960,000.00

Progress

Reported complete (DPWH)

Start Date

July 8, 2019

Target End

November 4, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.