Flood Control and Drainage20HH0089

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BRGY. SAWANG CALERO, CEBU CITY

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BRGY. SAWANG CALERO, CEBU CITY is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱4,897,000.00. Status: Reported complete (DPWH). Contractor on record: JCJD CONST. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at Brgy. Sawang Calero, Cebu City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Cebu City DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

13 projects · ₱48.2M total · 0 flags

Other projects by this contractor

No sat.

CLUSTER: CONSTRUCTION/REHABILITATION OF ACCESSIBILITY FACILITIES FOR PHYSICALLY CHALLENGED PERSON AT 1) REGIONAL OFFICE 7, SOUTH ROAD PROPERTIES, 2) CEBU 1ST DEO, BRGY. POBLACION, MEDELLIN, CEBU, 3) CEBU 5TH DEO, BRGY. GUINSAY, DANAO CITY, CEBU, 4) BOHOL

Region VII, Region VII

2019₱23.0M
Reported complete (DPWH)
No sat.

CLUSTER PROJECT: CONSTRUCTION OF RAIN WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS-RAIN WATER COLLECTORS IN PUBLIC FACILITIES-19 UNITS, 1. 1 UNIT-CITY CENTRAL ELEMENTARY SCHOOL, CEBU CITY, 2. 2 UNITS-SAN ROQUE ELEMENTARY SCHOOL, TALISAY CITY

Region VII, Region VII

2020₱4.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REPAIR/REHAB/COMPLETION/IMPROVEMENT OF MULTI-PURPOSE BUILDING BARANGAY TAPUL, TALISAY CITY, CEBU

Cebu 1st DEO, Region VII

2019₱4.0M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BRGY. CALAMBA, CEBU CITY

Cebu City DEO, Region VII

2020₱2.9M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS - CONCRETING OF ROAD, BRGY. HIPODROMO, CEBU CITY

Cebu City DEO, Region VII

2020₱2.0M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURE - MULTI PURPOSE / FACILITIES - CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BRGY. MABINI, CEBU CITY

Cebu City DEO, Region VII

2020₱1.5M
Reported complete (DPWH)
View all 13 projects →

4. Implementation

Contract Amount

₱4,897,000.00

Progress

Reported complete (DPWH)

Start Date

October 20, 2020

Target End

March 9, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.