Water Provision and Storage25HO0073

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION (COMPLETION) OF WATER SUPPLY SYSTEM, BARANGAY TIGUIB, BADIAN, CEBU

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION (COMPLETION) OF WATER SUPPLY SYSTEM, BARANGAY TIGUIB, BADIAN, CEBU is a DPWH-tracked public work in Cebu 7th DEO, Region VII. Reported contract value: ₱2,969,846.93. Status: Past target date (DPWH On-Going). Contractor on record: MACTAN ROCK INDUSTRIES INC. Figures trace to dpwh.

Cebu 7th DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱150,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tubod River Flood Control, Barangay Tubod-Duguan, Dumanjug, Cebu (Phase 3)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-25-0008820

₱2,391,464,863.61 · FY2025

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

6 projects · ₱146.5M total · 0 flags

4. Implementation

Contract Amount

₱2,969,846.93

Progress

Past target date (DPWH On-Going)

Start Date

February 19, 2025

Target End

May 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.