Water Provision and Storage25HO0093

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION (COMPLETION) OF WATER SUPPLY SYSTEM, BARANGAY BASIAO, BADIAN, CEBU

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION (COMPLETION) OF WATER SUPPLY SYSTEM, BARANGAY BASIAO, BADIAN, CEBU is a DPWH-tracked public work in Cebu 7th DEO, Region VII. Reported contract value: ₱2,968,720.77. Status: Past target date (DPWH On-Going). Contractor on record: MACTAN ROCK INDUSTRIES INC. Figures trace to dpwh.

Cebu 7th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱150,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tubod River Flood Control, Barangay Tubod-Duguan, Dumanjug, Cebu (Phase 3)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cebu 7th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

6 projects · ₱146.5M total · 0 flags

4. Implementation

Contract Amount

₱2,968,720.77

Progress

Past target date (DPWH On-Going)

Start Date

February 19, 2025

Target End

May 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.