Buildings and Facilities20MF0082

CONSTRUCTION OF MULTI-PURPOSE BUILDING FOR DIALYSIS CENTER, NEW CAPITOL SITE, BRGY. KENRAM, ISULAN, SULTAN KUDARAT

CONSTRUCTION OF MULTI-PURPOSE BUILDING FOR DIALYSIS CENTER, NEW CAPITOL SITE, BRGY. KENRAM, ISULAN, SULTAN KUDARAT is a DPWH-tracked public work in Sultan Kudarat 1st DEO, Region XII. Reported contract value: ₱19,778,440.62. Status: Reported complete (DPWH). Contractor on record: ALPXR CONST. Figures trace to dpwh.

Sultan Kudarat 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control of Ala River Basin (Mapantig Section), Isulan, Sultan Kudarat
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-20-0018362

₱15,097,691.00 · FY2020

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱19,778,440.62

Progress

Reported complete (DPWH)

Start Date

September 14, 2020

Target End

August 31, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.