Construction of Revetment23DF0021

Construction of Revetment along Manila Bay, Barangay San Rafael 4 Phase 4, Noveleta, Cavite

Construction of Revetment along Manila Bay, Barangay San Rafael 4 Phase 4, Noveleta, Cavite is a DPWH-tracked public work in NOVELETA (CAVITE), CAVITE, Region IV-A. Reported contract value: ₱96,500,000.00. Status: Reported complete (DPWH). Contractor on record: GRAIA CONST CORP. Figures trace to sumbong.

NOVELETA (CAVITE), CAVITE, Region IV-A
Region: Region IV-A

Follow the peso

3 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2023 · ₱5,000

    Probable match · score 0.87

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROXI-23-0024870 · ₱60,191 · release to the district office, not itemized per project

    Possible match · score 0.58

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱48,507,556 · N.B. AVILA CONSTRUCTION - CAVITE

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2023-01-07 → 2024-04-16

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: Construction of Revetment along Manila Bay, Barangay San Rafael 4 Phase 4, Noveleta, Cavite

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System in Barangay Binakayan (Covelandia Road and Tirona Highway), Kawit, Cavite
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-23-0024870

₱60,191.00 · FY2023

Released to Davao de Oro State College (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

23DF0016

₱48,507,556.17 · N.B. AVILA CONSTRUCTION - CAVITE

Award / contract ref: 23DF0016

Confirmed (exact contract ID) · 100%

23DF0019

₱57,267,391.33 · GRAIA CONST CORP

Award / contract ref: 23DF0019

Confirmed (exact contract ID) · 100%

23DF0018

₱48,484,439.09 · J.M. MALIGAYA CONSTRUCTION & CONSTRUCTION SUPPLY

Award / contract ref: 23DF0018

Confirmed (exact contract ID) · 100%

23DF0021

₱95,505,003.76 · GRAIA CONST CORP

Award / contract ref: 23DF0021

Confirmed (exact contract ID) · 100%

23DF0015

₱48,519,555.30 · N.B. AVILA CONSTRUCTION - CAVITE

Award / contract ref: 23DF0015

Contractor

B

67 projects · ₱4.8B total · 23 flags

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Reported complete (DPWH)

Start Date

February 19, 2023

Target End

January 22, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region IV-A (CALABARZON)Cavite
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.