Construction of Flood Mitigation Structure22BG0021

Construction of Cagayan River Flood Control Project, Brgy. Labinab Pequeño, Reina Mercedes, Isabela

Construction of Cagayan River Flood Control Project, Brgy. Labinab Pequeño, Reina Mercedes, Isabela is a DPWH-tracked public work in REINA MERCEDES (ISABELA), ISABELA, Region II. Reported contract value: ₱43,460,547.86. Status: Reported complete (DPWH). Contractor on record: MAR-DEB CONST & DEVELOPMENT CORP FORMERLY: MAR-DEB CONST & DEVELOPMENT. Figures trace to sumbong.

REINA MERCEDES (ISABELA), ISABELA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cagayan River Flood Control Project, Brgy. Labinab Peque±o, Reina Mercedes, Isabela
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-F-22-0004910

₱-391,688.00 · FY2022

Released to Diliman Campus (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002982

₱412,104,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003013

₱65,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

25 projects · ₱1.6B total · 8 flags

4. Implementation

Contract Amount

₱43,460,547.86

Progress

Reported complete (DPWH)

Start Date

February 14, 2022

Target End

March 15, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.