Construction of Flood Mitigation Structure24NB0012

Construction of Bank Protection along Agusan River (Magtuyon Section) San Luis, Agusan del Sur

Construction of Bank Protection along Agusan River (Magtuyon Section) San Luis, Agusan del Sur is a DPWH-tracked public work in SAN LUIS (AGUSAN DEL SUR), AGUSAN DEL SUR, Region XIII. Reported contract value: ₱77,199,705.93. Status: Reported complete (DPWH). Contractor on record: J M LACORTE CONST / LEXICON DEVELOPMENT CORP. Figures trace to sumbong.

SAN LUIS (AGUSAN DEL SUR), AGUSAN DEL SUR, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project along Agusan River, Esperanza, Agusan del Sur
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0005960

₱8,359,028.00 · FY2024

Released to Caraga State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0016790

₱434,031.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0009259

₱1,880,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0000458

₱112,315.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0014762

₱174,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0001754

₱645,114.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱77.2M total · 0 flags

4. Implementation

Contract Amount

₱77,199,705.93

Progress

Reported complete (DPWH)

Start Date

April 17, 2024

Target End

April 25, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.