Rehabilitation / Major Repair of Drainage Structure22HN0070

Rehabilitation of Drainage with Sidewalk at G. Ouna St., Alang Alang Mandaue City

Rehabilitation of Drainage with Sidewalk at G. Ouna St., Alang Alang Mandaue City is a DPWH-tracked public work in CEBU, Region VII. Reported contract value: ₱4,939,949.55. Status: Reported complete (DPWH). Contractor on record: PLD CONST AND DEVELOPMENT INC FORMERLY: PLD CONST. Figures trace to sumbong.

CEBU, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at Barangay Alegria, Sta. 5+000 - Sta. 6+000, Tuburan, Cebu
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-22-0005595

₱19,407,042.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003106

₱534,892,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002799

₱45,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVII-22-0004986

₱5,128,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVII-22-0004987

₱459,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

230 projects · ₱5.3B total · 0 flags

Other projects by this contractor

CONST. OF FLOOD CONTROL STRUCTURE ALONG MARANDING RIVER, INCL. ROW, PACKAGE 6, LANAO DEL NORTE

Region X, Region X

2024₱157.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE FACILITY (LABANGON PUBLIC MARKET), BRGY. LABANGON, CEBU CITY, CEBU

Region VII, Region VII

2023₱140.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (LANAO CULTURAL CENTER), KAPATAGAN NATIONAL HIGH SCHOOL, BARANGAY POBLACION, KAPATAGAN, LANO DEL NORTE

Lanao del Norte 2nd DEO, Region X

2022₱118.2M
Reported complete (DPWH)
No sat.

CLUSTER G PREVENTIVE MAINTENANCE OF VARIOUS ROAD PROJECTS IN LANAO DEL NORTE1) MALABANG-DOBLESTON-TUKURAN RD - K1974 + 000 - K1975 + 300 =PHP62,465,415.002) MALABANG-DOBLESTON-TUKURAN RD - K1975 + 300 - K1977 + 560

Region X, Region X

2024₱114.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS, N. BACALSO AVE (CEBU SOUTH RD) - K0111+006.00 - K0111+912.00 AND K0113+905.00 - K0114+433.00

Cebu 2nd DEO, Region VII

2023₱98.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

PREVENTIVE MAINTENANCE ALONG LINAMON-ZAMBOANGA ROAD K1550+334-K1552+981, BACOLOD, LANAO DEL NORTE

Lanao del Norte 1st DEO, Region X

2021₱96.5M
Reported complete (DPWH)
View all 230 projects →

4. Implementation

Contract Amount

₱4,939,949.55

Progress

Reported complete (DPWH)

Start Date

March 30, 2022

Target End

July 8, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.