Buildings and Facilities18MG0192

CONSTRUCTION OF 1 UNIT-2STY 4CL AT LAMBUSONG ES, SURALLAH, SOUTH COTABATO

CONSTRUCTION OF 1 UNIT-2STY 4CL AT LAMBUSONG ES, SURALLAH, SOUTH COTABATO is a DPWH-tracked public work in South Cotabato 2nd DEO, Region XII. Reported contract value: ₱8,560,671.60. Status: Reported complete (DPWH). Contractor on record: ILON MULTIBUILDERS CO FORMERLY: SHERATANNOR ENGINEERING CONST. Figures trace to dpwh.

South Cotabato 2nd DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bank Protection along Buayan River, General Santos City, South Cotabato
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

South Cotabato 2nd DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱8,560,671.60

Progress

Reported complete (DPWH)

Start Date

July 3, 2018

Target End

October 30, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.