Construction of Flood Mitigation Structure23BF0020

Construction of Siffu River Flood Control Project (Barangay San Jose Section), Sta. 0+000 - Sta. 0+600, Barangay San Jose, Quirino, Isabela,

Construction of Siffu River Flood Control Project (Barangay San Jose Section), Sta. 0+000 - Sta. 0+600, Barangay San Jose, Quirino, Isabela, is a DPWH-tracked public work in QUIRINO (ISABELA), ISABELA, Region II. Reported contract value: ₱48,231,388.59. Status: Reported complete (DPWH). Contractor on record: DANYSONS CONST AND DEVELOPMENT CORP FORMERLY: DANYSONS CONST. Figures trace to sumbong.

QUIRINO (ISABELA), ISABELA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Mallig River Flood Control Project (Maligaya Section), Mallig, Isabela
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Isabela 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

138 projects · ₱4.1B total · 11 flags

Other projects by this contractor

View all 138 projects →

4. Implementation

Contract Amount

₱48,231,388.59

Progress

Reported complete (DPWH)

Start Date

February 27, 2023

Target End

September 24, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.