Construction of Flood Mitigation Structure24PM0029

Construction of Lias Flood Control Structure (Section 1L), Sta. 055+825 - Sta. 056+700 (Right Side), Barlig, Mountain Province

Construction of Lias Flood Control Structure (Section 1L), Sta. 055+825 - Sta. 056+700 (Right Side), Barlig, Mountain Province is a DPWH-tracked public work in BARLIG (MOUNTAIN PROVINCE), MOUNTAIN PROVINCE, Cordillera Administrative Region. Reported contract value: ₱96,500,000.00. Status: Reported complete (DPWH). Contractor on record: E T LATAWAN CONST. Figures trace to sumbong.

BARLIG (MOUNTAIN PROVINCE), MOUNTAIN PROVINCE, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Binabagan Flood Control, Bunot, Paracelis, Mountain Province
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-CAR-24-0008745

₱5,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-CAR-24-0008517

₱1,381,720.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-CAR-24-0008530

₱127,605.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-CAR-24-0005523

₱64,940.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

49 projects · ₱2.1B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF CANAN BRIDGE, LA PAZ, ABRA

Abra DEO, Cordillera Administrative Region

2024₱140.2M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONSTRUCTION OF CALABA VIADUCT PHASE I, CALABA, BANGUED, ABRA

Abra DEO, Cordillera Administrative Region

2024₱139.9M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONSTRUCTION OF CALABA VIADUCT PHASE 2, CALABA, BANGUED, ABRA

Abra DEO, Cordillera Administrative Region

2024₱139.8M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF OTIP BRIDGE, TUBO, ABRA

Abra DEO, Cordillera Administrative Region

2024₱138.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONSTRUCTION OF SINALANG-PALAO BRIDGE APPROACHES, PALAO, BANGUED, ABRA

Abra DEO, Cordillera Administrative Region

2024₱137.5M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONSTRUCTION OF SINALANG-PALAO BRIDGE, BANGUED, ABRA

Abra DEO, Cordillera Administrative Region

2024₱137.4M
Past target date (DPWH On-Going)
View all 49 projects →

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Reported complete (DPWH)

Start Date

February 26, 2024

Target End

November 2, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.