GAA 2025 LFP25RE0019

CONSTRUCTION (COMPLETION) OF DPWH BUILDING OF NEGROS OCCIDENTAL SUB DEO, SAN CARLOS CITY, NEGROS OCCIDENTAL

CONSTRUCTION (COMPLETION) OF DPWH BUILDING OF NEGROS OCCIDENTAL SUB DEO, SAN CARLOS CITY, NEGROS OCCIDENTAL is a DPWH-tracked public work in Negros Occidental 5th DEO, Negros Island Region. Reported contract value: ₱29,428,859.60. Status: Past target date (DPWH On-Going). Contractor on record: RKVT CONST. Figures trace to dpwh.

Negros Occidental 5th DEO, Negros Island Region
Region: Negros Island Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure of Matagoy Creek, Silay City, Negros Occidental
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Negros Occidental 5th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

27 projects · ₱1.0B total · 0 flags

Other projects by this contractor

No sat.

CSSP, SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, REHAB. OF DAMAGED PAVED ROAD AT CAMPALANAS-LOWER CABANGCALAN ROAD, LAZI, SIQUIJOR

Region VII, Region VII

2024₱164.0M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD CONTROL STRUCTURES OF ANDOON RIVER (UPSTREAM) ALONG BACOLOD-MURCIA-DS BENEDICTO-SN CARLOS CITY ROAD (S00427NR), SAN CARLOS CITY, NEGROS OCCIDENTAL

Region VI, Region VI

2024₱144.8M
Reported complete (DPWH)

CONSTRUCTION OF FLOOD CONTROL STRUCTURES OF ANDOON RIVER ALONG BACOLOD-MURCIA-DS BENEDICTO-SN CARLOS CITY ROAD (S00427NR), SAN CARLOS CITY, NEGROS OCCIDENTAL

Region VI, Region VI

2024₱144.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (DOWNSTREAM) AT CAMOGAO, EN

Siquijor DEO, Negros Island Region

2024₱96.5M
Past target date (DPWH On-Going)
No sat.

PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY ALONG JCT NATL RD SAGAY-BATO-DIAN-AY-MARCELO-BALEA JCT RD (S00426NR) - K0103 + 083 - K0104 + 000, K0112 + 000 - K0114 + 000, K0121 + 435 - K0122 + 106

Negros Occidental 5th DEO, Negros Island Region

2025₱96.3M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE OF MAGBABOY RIVER (SEGMENT 1), ALONG BACOLOD NORTH RD, SAN CARLOS CITY, NEGROS OCCIDENTAL

Negros Occidental 5th DEO, Negros Island Region

2025₱95.5M
Past target date (DPWH On-Going)
View all 27 projects →

4. Implementation

Contract Amount

₱29,428,859.60

Progress

Past target date (DPWH On-Going)

Start Date

September 3, 2025

Target End

May 27, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.