Flood Control and Drainage22BI0097

ORGANIZATION OUTCOME 2: FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM IMPROVEMENT OF MANAMTAM RIVER CONTROL ALONG MATUNO RIVER

ORGANIZATION OUTCOME 2: FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM IMPROVEMENT OF MANAMTAM RIVER CONTROL ALONG MATUNO RIVER is a DPWH-tracked public work in Nueva Vizcaya DEO, Region II. Reported contract value: ₱73,500,000.00. Status: Reported complete (DPWH). Contractor on record: J E L CONST & SUPPLY. Figures trace to dpwh.

Nueva Vizcaya DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Flood Control and Drainage Structure along Sta. Cruz River, Salinas Section 1, Bambang, Nueva Vizcaya
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Nueva Vizcaya DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱73,500,000.00

Progress

Reported complete (DPWH)

Start Date

December 28, 2022

Target End

October 6, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.