Construction of Flood Mitigation Structure24HJ0021

Construction of Flood Control along Calamba River, Guihulngan City, Negros Oriental

Construction of Flood Control along Calamba River, Guihulngan City, Negros Oriental is a DPWH-tracked public work in CITY OF GUIHULNGAN (NEGROS ORIENTAL), NEGROS ORIENTAL, Region VII. Reported contract value: ₱29,400,000.00. Status: Reported complete (DPWH). Contractor on record: MIGHTY HOK SUMMIT CONST & DEVELOPMENT CORP. Figures trace to sumbong.

CITY OF GUIHULNGAN (NEGROS ORIENTAL), NEGROS ORIENTAL, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Calamba River, Guihulngan City, Negros Oriental
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0007805

₱1,487,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0002591

₱233,883.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0007808

₱137,000.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱29,400,000.00

Progress

Reported complete (DPWH)

Start Date

February 7, 2024

Target End

October 9, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.