Flood Control and Drainage18IL0044

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS/CONSTRUCTION OF SAN ROQUE RIVER FLOOD CONTROL ALONG BDRY. SO. LEYTE-MAASIN-MACROHON-SOGOD-DAANG MAHARLIKA (S00194LT) MACROHON, SOUTHERN LEYTE(CONSTRUCTION OF FLOOD MITIGATION STR

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS/CONSTRUCTION OF SAN ROQUE RIVER FLOOD CONTROL ALONG BDRY. SO. LEYTE-MAASIN-MACROHON-SOGOD-DAANG MAHARLIKA (S00194LT) MACROHON, SOUTHERN LEYTE(CONSTRUCTION OF FLOOD MITIGATION STR is a DPWH-tracked public work in Southern Leyte 1st DEO, Region VIII. Reported contract value: ₱11,759,999.95. Status: Reported complete (DPWH). Contractor on record: CEAN CONST. Figures trace to dpwh.

Southern Leyte 1st DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

105 projects · ₱1.3B total · 0 flags

Other projects by this contractor

No sat.

MAASIN AIRPORT DEVELOPMENT PROJECT (IMPROVEMENT OF RUNWAY STRIP) ,MAASIN CITY, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2024₱97.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN) - ACCESS ROAD LEADING TO MAASIN AIRPORT INCLUDING RUNWAY, MAASIN CITY, SOUTHERN LEY

Southern Leyte 1st DEO, Region VIII

2023₱96.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETOWRK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - TACLOBAN-BAYBAY-SOUTH ROAD - K0995+000-K0996+200, K1002+800-K1003+800

Leyte 5th DEO, Region VIII

2019₱83.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN, CONSTRUCTION OF ACCESS ROAD LEADING TO MAASIN AIRPORT INCLUDING RUNWAY (SEGMENT 2),

Southern Leyte 1st DEO, Region VIII

2024₱67.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN, ACCESS ROAD LEADING TO MAASIN AIRPORT INCLUDING RUNWAY (SEGMENT 2), MAASIN CITY, SO

Southern Leyte 1st DEO, Region VIII

2024₱49.0M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, LIMASAWA CIRCUMFERENTIAL ROAD, LIMASAWA, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2020₱49.0M
Reported complete (DPWH)
View all 105 projects →

4. Implementation

Contract Amount

₱11,759,999.95

Progress

Reported complete (DPWH)

Start Date

March 13, 2018

Target End

June 30, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.