Flood Control and Drainage24KE0038

CONSTRUCTION OF RIVER CONTROL ALONG LUMAD BRIDGE,CAMIGUIN CIRCUMFERENTIAL ROAD,MAMBAJAO,CAMIGUIN

CONSTRUCTION OF RIVER CONTROL ALONG LUMAD BRIDGE,CAMIGUIN CIRCUMFERENTIAL ROAD,MAMBAJAO,CAMIGUIN is a DPWH-tracked public work in Camiguin DEO, Region X. Reported contract value: ₱46,798,954.67. Status: Reported complete (DPWH). Contractor on record: SHEEN-SHEEN CONST CORP FORMERLY: SHEEN-SHEEN CONST. Figures trace to dpwh.

Camiguin DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 75%

UACS
18001
Amount
₱53,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure ( Rangas River ) along Jct. Nato - Sabang Coastal Road, Barangay Telegrafo, San Jose, Camarines Sur
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Camiguin DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Contract ID No. 24KE0038 Construction of River Con

₱46,798,954.67 · SHEEN-SHEEN CONSTRUCTION

4. Implementation

Contract Amount

₱46,798,954.67

Progress

Reported complete (DPWH)

Start Date

May 28, 2024

Target End

December 3, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.