Flood Control and Drainage19BD0152

REPAIR/MAINTENANCE OF FLOOD CONTROL STRUCTURE AT PATA, ENRILE, CAGAYAN

REPAIR/MAINTENANCE OF FLOOD CONTROL STRUCTURE AT PATA, ENRILE, CAGAYAN is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱43,932,868.97. Status: Reported complete (DPWH). Contractor on record: MEGAY CONST INC FORMERLY: MEGAY CONST. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    SARO SARO-ROXI-19-0018277 · ₱250,056 · release to the district office, not itemized per project

    Possible match · score 0.74

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱43,932,869 · MEGAY CONSTRUCTION

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-02-04 → 2025-06-03

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Cagayan

Based on the coordinates published with the DPWH record and NOAH file Cagayan.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: REPAIR/MAINTENANCE OF FLOOD CONTROL STRUCTURE AT PATA, ENRILE, CAGAYAN

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-19-0018277

₱250,056.00 · FY2019

Released to School (Davao del Sur National High School) 0911230 - Digos City National High (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

REPAIR/MAINTENANCE OF FLOOD CONTROL STRUCTURE AT P

₱43,932,868.97 · MEGAY CONSTRUCTION

Award / contract ref: 19BD0152

Contractor

C

130 projects · ₱5.6B total · 2 flags

Other projects by this contractor

No sat.

REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CAGAYAN RIVER FLOOD MANAGEMENT PROJECTS, BRGY. ANQUIRAY, AMULUNG, CAGAYAN (DOWNSTREAM) STA. 0+320 - STA. 0+520

Cagayan 3rd DEO, Region II

2024₱136.4M
Past target date (DPWH On-Going)
No sat.

REHABILITATION OF FLOOD CONTROL MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CAGAYAN RIVER FLOOD MANAGEMENT PROJECTS, BRGY. PATA, ENRILE, CAGAYAN (DOWNSTREAM) STA. 0+230 - STA. 0+430

Cagayan 3rd DEO, Region II

2024₱136.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - PEÑABLANCA- CALLAO CAVE RD - K0482+600 - K0482+692

Cagayan 3rd DEO, Region II

2024₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - PEÑABLANCA - CALLAO CAVE RD. - PHASE III PACKAGE 5

Cagayan 3rd DEO, Region II

2023₱96.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - PEÑABLANCA - CALLAO CAVE RD. - PHASE III PACKAGE 4

Cagayan 3rd DEO, Region II

2023₱96.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - PEÑABLANCA - CALLAO CAVE RD. - PHASE III PACKAGE 2

Cagayan 3rd DEO, Region II

2023₱96.4M
Reported complete (DPWH)
View all 130 projects →

4. Implementation

Contract Amount

₱43,932,868.97

Progress

Reported complete (DPWH)

Start Date

February 21, 2020

Target End

August 5, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region II (Cagayan Valley)CagayanEnrileBarangay II
Storms whose wind field reached it
Peilou 2026Noul 2026Fung-Wong 2025Matmo 2025Ragasa 2025
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.