Construction of Slope Protection Structure24CI0006

Construction Slope Protection Structure along Abacan River, Barangay Anunas to Barangay Malabañas (Phase II), Angeles City, Pampanga

Construction Slope Protection Structure along Abacan River, Barangay Anunas to Barangay Malabañas (Phase II), Angeles City, Pampanga is a DPWH-tracked public work in ANGELES CITY (PAMPANGA), PAMPANGA, Region III. Reported contract value: ₱48,979,865.38. Status: Reported complete (DPWH). Contractor on record: NICLEDON CONST. Figures trace to sumbong.

ANGELES CITY (PAMPANGA), PAMPANGA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Pampanga River, Apalit, Pampanga
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008254

₱1,156,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0017639

₱458,088.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0018104

₱90,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0018317

₱121,051.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008256

₱107,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008158

₱156,487.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

15 projects · ₱578.8M total · 1 flags

Other projects by this contractor

View all 15 projects →

4. Implementation

Contract Amount

₱48,979,865.38

Progress

Reported complete (DPWH)

Start Date

February 16, 2024

Target End

July 31, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.