Flood Control and Drainage24CL0037

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BANCAL DANAC BUNGA SECTION, BOTOLAN, ZAMBALES

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BANCAL DANAC BUNGA SECTION, BOTOLAN, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱98,910,080.05. Status: Reported complete (DPWH). Contractor on record: NICLEDON CONST 36234. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Tapuac - Sta Maria River, Masinloc, Zambales ( Phase 1 )
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Zambales 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 36234

12 projects · ₱482.6M total · 0 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM; CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUITANGIL RIVER, DOWNSTREAM OF OF QUITANGIL BRIDGE, MAGALANG, PAMPANGA

Pampanga 3rd DEO, Region III

2025₱103.1M
Past target date (DPWH On-Going)
No sat.

REPAIR/REHABILITATION/IMPROVEMENT OF SLOPE PROTECTION ALONG TARLAC RIVER CONTROL LEFT DIKE, TIBAG SECTION, TARLAC CITY, TARLAC

Tarlac DEO, Region III

2024₱76.9M
Reported complete (DPWH)
No sat.

BRIDGE PROGRAM-REPLACEMENT OF PERMANENT WEAK BRIDGES, SAN FERNANDO FLYOVER ALONG JOSE ABAD SANTOS AVENUE (JASA), PROVINCE OF PAMPANGA

Region III, Region III

2022₱67.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY MESALIPIT - TALBA, BACOLOR, PAMPANGA

Pampanga 1st DEO, Region III

2025₱37.3M
Ongoing (DPWH-reported)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF TALBA - TINAJERO ROAD INCLUDING DRAINAGE SYSTEM, BACOLOR, PAMPA

Pampanga 1st DEO, Region III

2022₱37.2M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF MAPALAD - CANDATING ROAD, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2022₱23.2M
Reported complete (DPWH)
View all 12 projects →

4. Implementation

Contract Amount

₱98,910,080.05

Progress

Reported complete (DPWH)

Start Date

February 15, 2024

Target End

January 9, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.