Roads20HA0028

OFF-CARRIAGEWAY IMPROVEMENT-JCT. (TNR) MARIBOJOC-ANTEQUERA-CATAGBACAN (LOON) - K0015+616-K0015+643, K0015+665-K0015+692, K0015+722-K0016+979

OFF-CARRIAGEWAY IMPROVEMENT-JCT. (TNR) MARIBOJOC-ANTEQUERA-CATAGBACAN (LOON) - K0015+616-K0015+643, K0015+665-K0015+692, K0015+722-K0016+979 is a DPWH-tracked public work in Bohol 1st DEO, Region VII. Reported contract value: ₱12,546,000.00. Status: Reported complete (DPWH). Contractor on record: A A DE VERA CONST 6191. Figures trace to dpwh.

Bohol 1st DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱12,546,000.00

Progress

Reported complete (DPWH)

Start Date

December 1, 2020

Target End

February 20, 2021