GAA 2024 SSP24HC0157

BIP- PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATERWORKS SYSTEM, UBAY, BOHOL

BIP- PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATERWORKS SYSTEM, UBAY, BOHOL is a DPWH-tracked public work in Bohol 2nd DEO, Region VII. Reported contract value: ₱49,400,000.00. Status: Past target date (DPWH On-Going). Contractor on record: ZLREJ TRADING AND CONST CORP. Figures trace to dpwh.

Bohol 2nd DEO, Region VII
Region: Region VII

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2024 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱49,400,000 · ZLREJ TRADING AND CONST CORP

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    52% reported · imagery 2015-07-12 → 2025-08-23

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: BIP- PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATERWORKS SYSTEM, UBAY, BOHOL

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of San Francisco Bridge Flood Control Structure, Ubay, Bohol
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bohol 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

CONSTRUCTION PROJECT

₱49,400,000.00 · ZLREJ TRADING AND CONST CORP

Award / contract ref: 24HC0157

Contractor

C

119 projects · ₱8.5B total · 1 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, CEBU SOUTH COASTAL RD - (S00015CB) CHAINAGE 510 - CHAINAGE 1019

Region VII, Region VII

2025₱221.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, CEBU SOUTH COASTAL RD - CHAINAGE 0 - CHAINAGE 510

Region VII, Region VII

2024₱192.9M
Past target date (DPWH On-Going)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF STORM SURGE PROTECTION STRUCTURES AT BRGY. GUINTABOAN, UBAY, BOHOL

Region VII, Region VII

2024₱192.8M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, CANSAGA BAY BR. (B00613CB) ALONG CANSAGA BAY BRIDGE, CEBU

Region VII, Region VII

2022₱173.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES, VIADUCT BR. (B00081CB) ALONG CEBU SOUTH COASTAL RD

Region VII, Region VII

2024₱173.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, MARCELO FERNAN BR. (B00619CB) ALONG MARCELO B. FERNAN BR. & APPROACHES

Region VII, Region VII

2024₱173.7M
Reported complete (DPWH)
View all 119 projects →

4. Implementation

Contract Amount

₱49,400,000.00

Progress

Past target date (DPWH On-Going)

Start Date

March 19, 2025

Target End

November 27, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VII (Central Visayas)BoholUbayLomangog
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.