Flood Control and Drainage25BG0146

OO2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONST/ REHAB OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVER-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER BASIN ALONG BARANGAY CALACCAB,

OO2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONST/ REHAB OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVER-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER BASIN ALONG BARANGAY CALACCAB, is a DPWH-tracked public work in Isabela 3rd DEO, Region II. Reported contract value: ₱93,599,286.98. Status: Past target date (DPWH On-Going). Contractor on record: INFINITI CONST AND DEVELOPMENT CORP. Figures trace to dpwh.

Isabela 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Pinacanauan River Flood Control Structure, Barangay Dipusu, San Mariano, Isabela
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Isabela 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

13 projects · ₱482.1M total · 1 flags

Other projects by this contractor

No sat.

OO2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM - CONST/REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER BASIN, BRGY. ANIOG,

Isabela 3rd DEO, Region II

2025₱93.6M
Past target date (DPWH On-Going)
No sat.

OO2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONST/ REHAB OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER BASIN ALONG BRGY. CENTRO III,

Isabela 3rd DEO, Region II

2025₱93.6M
Past target date (DPWH On-Going)
No sat.

Construction of Flood Control Structure along Cagayan River, Barangays PISBAKAL, Angadanan, Isabela

ANGADANAN (ISABELA), ISABELA, Region II

2024₱77.2M
Reported complete (DPWH)
No sat.

Construction of Cagayan River Flood Control Project, Barangay San Guillermo (Phase III), Angadanan, Isabela

ANGADANAN (ISABELA), ISABELA, Region II

2024₱48.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM(BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONSTRUCTION (COMPLETION) OF SINALUGAN BRIDGE, BARANGAY BUENAVISTA,

Isabela 3rd DEO, Region II

2025₱24.7M
Past target date (DPWH On-Going)
No sat.

CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY CENTRO II - BARANGAY CENTRO I, ANGADANAN, ISABELA

Isabela 3rd DEO, Region II

2024₱9.9M
Past target date (DPWH On-Going)
View all 13 projects →

4. Implementation

Contract Amount

₱93,599,286.98

Progress

Past target date (DPWH On-Going)

Start Date

June 2, 2025

Target End

April 24, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.