Construction of Slope Protection Structure22HB0009

Construction of Slope Protection along Jct. (TER) Guidulman - Anda - Badiang - Cogtong Road, Sta. 21+860-Sta. 22+000 (Left Side), Sta. 21+934-Sta.21+989 (Right Side), Anda , Bohol

Construction of Slope Protection along Jct. (TER) Guidulman - Anda - Badiang - Cogtong Road, Sta. 21+860-Sta. 22+000 (Left Side), Sta. 21+934-Sta.21+989 (Right Side), Anda , Bohol is a DPWH-tracked public work in ANDA (BOHOL), BOHOL, Region VII. Reported contract value: ₱77,199,954.39. Status: Reported complete (DPWH). Contractor on record: FUENTABUILT CONST CORP / M R VARGAS CONST CORP FORMERLY: M R VARGAS CONST. Figures trace to sumbong.

ANDA (BOHOL), BOHOL, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at Barangay Tupas (Antequera) along Abatan River - Sta. 000+000.00 - Sta. 001+000.00, Antequera, Bohol
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002955

₱842,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002897

₱10,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱77,199,954.39

Progress

Reported complete (DPWH)

Start Date

April 12, 2022

Target End

December 21, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.