Construction of Flood Mitigation Structure24HB0008

Construction of Gabayan River Flood Control, Candijay, Bohol

Construction of Gabayan River Flood Control, Candijay, Bohol is a DPWH-tracked public work in CANDIJAY (BOHOL), BOHOL, Region VII. Reported contract value: ₱139,442,021.80. Status: Reported complete (DPWH). Contractor on record: FUENTABUILT CONST CORP / M R VARGAS CONST CORP FORMERLY: M R VARGAS CONST. Figures trace to sumbong.

CANDIJAY (BOHOL), BOHOL, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Abucayan Norte Flood Control, Abucayan Norte, Calape, Bohol
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0011391

₱1,351,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0008581

₱531,894.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0018685

₱225,560.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0011392

₱125,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱139,442,021.80

Progress

Reported complete (DPWH)

Start Date

June 11, 2024

Target End

May 11, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.