Construction of Flood Mitigation Structure24BG0109

Construction of Flood Control Structure along Cagayan River, Phase 3, Barangay Pappat, Angadanan, Isabela

Construction of Flood Control Structure along Cagayan River, Phase 3, Barangay Pappat, Angadanan, Isabela is a DPWH-tracked public work in ANGADANAN (ISABELA), ISABELA, Region II. Reported contract value: ₱77,159,066.51. Status: Reported complete (DPWH). Contractor on record: INFINITUM 888 CONST AND DEVELOPMENT CORP. Figures trace to sumbong.

ANGADANAN (ISABELA), ISABELA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cagayan River Flood Control Project, Barangay San Guillermo ( Phase III ) , Angadanan, Isabela
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0004352

₱1,853,487.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0009805

₱1,459,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0003846

₱276,213.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0004354

₱173,574.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010584

₱135,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

59 projects · ₱527.5M total · 2 flags

4. Implementation

Contract Amount

₱77,159,066.51

Progress

Reported complete (DPWH)

Start Date

May 9, 2024

Target End

February 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.