Construction of Flood Mitigation Structure23MC0020

Construction of Revetment along New Cebu River, President Roxas, North Cotabato

Construction of Revetment along New Cebu River, President Roxas, North Cotabato is a DPWH-tracked public work in PRESIDENT ROXAS (COTABATO (NORTH COTABATO)), COTABATO (NORTH COTABATO), Region XII. Reported contract value: ₱29,400,000.00. Status: Reported complete (DPWH). Contractor on record: LLABAN CONST & SUPPLY FORMERLY: LLABAN CON. Figures trace to sumbong.

PRESIDENT ROXAS (COTABATO (NORTH COTABATO)), COTABATO (NORTH COTABATO), Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Libungan River, Mirasol Alamada, North Cotabato
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cotabato 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱29,400,000.00

Progress

Reported complete (DPWH)

Start Date

March 24, 2023

Target End

October 30, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.