GAA 2025 OO-225PL0072

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE A

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE A is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱7,675,603.47. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: GADAV BUILDERS. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Biga River ,Bawac Banneng, Tanudan, Kalinga
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Lower Kalinga DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

10 projects · ₱34.2M total · 0 flags

Other projects by this contractor

No sat.

CONCRETING OF SITIO ASIBANGLAN, BRGY. BAGUMBAYAN FMR, BRGY. BAGUMBAYAN, TABUK CITY, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2022₱11.9M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - MT PROVINCE BDRY-CALANAN-PINUKPUK-ABBUT RD (CAGALUAN-CALANAN SECT) - K0472

Lower Kalinga DEO, Cordillera Administrative Region

2024₱5.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF CALAOCAN MULTI-PURPOSE BUILDING, RIZAL, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2024₱2.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, CALAOCAN, RIZAL, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2023₱2.0M
Reported complete (DPWH)
No sat.

COMPLETION OF CENTRO TANNUBONG WATERWORKS SYSTEM, IPIL, TABUK CITY, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2020₱993K
Reported complete (DPWH)
No sat.

CONSTRUCTION (COMPLETION) OF ACIGA FOOTBRIDGE (PHASE 2) IN PINUKPUK, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2021₱980K
Reported complete (DPWH)
View all 10 projects →

4. Implementation

Contract Amount

₱7,675,603.47

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

June 20, 2025

Target End

October 14, 2025