Construction of Flood Mitigation Structure23A00109

Construction of Flood Control Structure along Paratong-Subec, Cabittaogan Creek, Sta. Catalina, Ilocos Sur

Construction of Flood Control Structure along Paratong-Subec, Cabittaogan Creek, Sta. Catalina, Ilocos Sur is a DPWH-tracked public work in SANTA CATALINA (ILOCOS SUR), ILOCOS SUR, Region I. Reported contract value: ₱77,199,817.11. Status: Reported complete (DPWH). Contractor on record: BET CONST & SUPPLY / LEZA CONST & SUPPLY. Figures trace to sumbong.

SANTA CATALINA (ILOCOS SUR), ILOCOS SUR, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Sta. Maria River ( Package 2 ), Sta. Maria, Ilocos Sur
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Ilocos Sur 1st District Engineering Office · SARO 40 (₱23,603,513,542.02) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱77.2M total · 0 flags

4. Implementation

Contract Amount

₱77,199,817.11

Progress

Reported complete (DPWH)

Start Date

October 2, 2023

Target End

November 30, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.