Construction of Revetment24BG0062

Construction of Magat River Flood Control Structure, Brgy. Mallalatang Grande, Reina Mercedes, Isabela (Phase III)

Construction of Magat River Flood Control Structure, Brgy. Mallalatang Grande, Reina Mercedes, Isabela (Phase III) is a DPWH-tracked public work in REINA MERCEDES (ISABELA), ISABELA, Region II. Reported contract value: ₱49,475,237.33. Status: Reported complete (DPWH). Contractor on record: MAR-DEB CONST & DEVELOPMENT CORP FORMERLY: MAR-DEB CONST & DEVELOPMENT. Figures trace to sumbong.

REINA MERCEDES (ISABELA), ISABELA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Magat River Flood Control Structure, Brgy. Mallalatang Grande, Reina Mercedes, Isabela ( Phase III )
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0004352

₱1,853,487.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0009805

₱1,459,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0003846

₱276,213.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0004354

₱173,574.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010584

₱135,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

25 projects · ₱1.6B total · 8 flags

4. Implementation

Contract Amount

₱49,475,237.33

Progress

Reported complete (DPWH)

Start Date

March 18, 2024

Target End

October 30, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.