Flood Control and Drainage25BH0304

BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS /FACILITIES - CONSTRUCTION OF SINILI FLOOD CONTROL STRUCTURE, SECTION 3, AT BARANGAY SINILI, SANTIAGO CITY, ISABELA

BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS /FACILITIES - CONSTRUCTION OF SINILI FLOOD CONTROL STRUCTURE, SECTION 3, AT BARANGAY SINILI, SANTIAGO CITY, ISABELA is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱96,031,060.22. Status: Ongoing (DPWH-reported) (Not Yet Started (DPWH-reported)). Contractor on record: NTL BUILDERS AND DEVELOPER. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Sinili Flood Control Structure, Section 3, at Barangay Sinili, Santiago City, Isabela
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Isabela 4th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

179 projects · ₱4.0B total · 0 flags

4. Implementation

Contract Amount

₱96,031,060.22

Progress

Not Yet Started (DPWH-reported)

Start Date

Data not yet available

Target End

Data not yet available

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.