Flood Control and Drainage25PL0029

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL ALONG CHICO

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL ALONG CHICO is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱9,604,765.03. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: W V CONST. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure along Chico River at Barangay Suyang, Tabuk City, Kalinga
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Lower Kalinga DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

16 projects · ₱98.7M total · 0 flags

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES ROAD IMPROVEMENT OF PUGONG - WAGAS ROAD, PASIL, KALINGA

Upper Kalinga DEO, Cordillera Administrative Region

2023₱9.9M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES: CONSTRCUCTION OF BALENCIAGAO-BAGTAYAN-BALATOC ACCESS ROAD IN BRGY. BALENCIAGAO, PASIL, KALINGA.

Upper Kalinga DEO, Cordillera Administrative Region

2024₱9.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES CONSTRUCTION OF ACCESS ROAD LEADING TO MT.

Upper Kalinga DEO, Cordillera Administrative Region

2025₱9.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF LOCAL ROAD, BANTAY- PUTOT AND MAPAOAY, BRGY. IPIL

Lower Kalinga DEO, Cordillera Administrative Region

2025₱7.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF SABONAC FLOOD CONTROL ALON

Upper Kalinga DEO, Cordillera Administrative Region

2024₱6.4M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM: ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES, CONSTRUCTION OF ACCESS ROAD LEADING TO DALUPA INDIGENOUS COMMUNITY IN PASIL KALINGA AND TO LIGAYAN INDIGENOUS COMMUNITY, KI

Upper Kalinga DEO, Cordillera Administrative Region

2023₱5.9M
Reported complete (DPWH)
View all 16 projects →

4. Implementation

Contract Amount

₱9,604,765.03

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 27, 2025

Target End

August 2, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.