Bridges20BF0067

BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - MALLIG BRIDGE (B01158LZ) ALONG SANTIAGO -TUGUEGARAO ROAD, MALLIG, ISABELA

BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - MALLIG BRIDGE (B01158LZ) ALONG SANTIAGO -TUGUEGARAO ROAD, MALLIG, ISABELA is a DPWH-tracked public work in Isabela 2nd DEO, Region II. Reported contract value: ₱211,978,475.56. Status: Reported complete (DPWH). Contractor on record: R D INTERIOR JUNIOR CONST. Figures trace to dpwh.

Isabela 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱46,528,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Casili Flood Control Project in Mallig, Isabela
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Isabela 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱211,978,475.56

Progress

Reported complete (DPWH)

Start Date

October 5, 2020

Target End

January 13, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.