(RE-ADVERTISED) CONSTRUCTION OF MULTI- PURPOSE BUILDING IN BRGY. BINALIW, CALBAYOG CITY, SAMAR 1ST LD

(RE-ADVERTISED) CONSTRUCTION OF MULTI- PURPOSE BUILDING IN BRGY. BINALIW, CALBAYOG CITY, SAMAR 1ST LD is a DPWH-tracked public work in Samar 1st DEO, Region VIII. Reported contract value: ₱5,670,635.76. Status: Reported complete (DPWH). Contractor on record: ND CARANZO BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Samar 1st DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱28,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Binaliw River (Phase II), Brgy. Binaliw, Calbayog City, Samar
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0003016

₱265,102.00 · FY2017

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱5,670,635.76

Progress

Reported complete (DPWH)

Start Date

March 27, 2017

Target End

June 24, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.