Flood Control and Drainage25PI0059

CONSTN OF FLOOD CONTROL STRUCTURE ALONG BAYUDAN-CHICO RIVER, ALLIWEN- SUYO, STA. 52+227- STA.52+431(LS), STA. 52+986 - STA. 53+016(RS), STA. 53+154 - STA. 53+224(LS), STA. 53+753 - STA. 53+782(LS), BAUKO, MOUNTAIN PROVINCE

CONSTN OF FLOOD CONTROL STRUCTURE ALONG BAYUDAN-CHICO RIVER, ALLIWEN- SUYO, STA. 52+227- STA.52+431(LS), STA. 52+986 - STA. 53+016(RS), STA. 53+154 - STA. 53+224(LS), STA. 53+753 - STA. 53+782(LS), BAUKO, MOUNTAIN PROVINCE is a DPWH-tracked public work in Mountain Province 1st DEO, Cordillera Administrative Region. Reported contract value: ₱29,048,626.88. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: LONGBOAN CONST 50773. Figures trace to dpwh.

Mountain Province 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bayudan-Chico River, Alliwen - Suyo, Sta. 52+227 - Sta.52+431 (LS), Sta. 52+986 - Sta. 53+016 (RS), Sta. 53+154 - Sta. 53+224 (LS), Sta.53+753 - Sta. 53+782 (LS), Bauko, Mountain Province
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Mountain Province 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱29,048,626.88

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 13, 2025

Target End

November 5, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.