Construction of Flood Mitigation Structure23GQ0023

Construction of Flood Control Structure of Higalaman River (Downstream) along Bacolod North Rd, San Carlos City, Negros Occidental

Construction of Flood Control Structure of Higalaman River (Downstream) along Bacolod North Rd, San Carlos City, Negros Occidental is a DPWH-tracked public work in SAN CARLOS CITY (NEGROS OCCIDENTAL), NEGROS OCCIDENTAL, Region VI. Reported contract value: ₱91,674,989.91. Status: Reported complete (DPWH). Contractor on record: KENNETH CONST AND GEN MERCHANDISE. Figures trace to sumbong.

SAN CARLOS CITY (NEGROS OCCIDENTAL), NEGROS OCCIDENTAL, Region VI
Region: Region VI

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Minabuno River, Cadiz City, Negros Occidental
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Negros Occidental 5th District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱91,674,989.91

Progress

Reported complete (DPWH)

Start Date

March 2, 2023

Target End

December 24, 2023

5. Audit