Construction of Flood Mitigation Structure22PL0003

Construction of Flood Control Structure along Cal-owan River, Sta. 2 + 430 - Sta. 3 + 380 (Left Bank), Brgy. Ammacian to Brgy. Malagnat, Pinukpuk, Kalinga

Construction of Flood Control Structure along Cal-owan River, Sta. 2 + 430 - Sta. 3 + 380 (Left Bank), Brgy. Ammacian to Brgy. Malagnat, Pinukpuk, Kalinga is a DPWH-tracked public work in PINUKPUK (KALINGA), KALINGA, Cordillera Administrative Region. Reported contract value: ₱48,449,186.44. Status: Reported complete (DPWH). Contractor on record: JTM CONST / EGB CONST CORP FORMERLY: EGB CONST. Figures trace to sumbong.

PINUKPUK (KALINGA), KALINGA, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Cal-owan River, Sta. 2 + 430 - Sta. 3 + 380 (Left Bank), Brgy. Ammacian to Brgy. Malagnat, Pinukpuk, Kalinga
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002942

₱130,524,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002815

₱3,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-CAR-22-0006269

₱1,561,218.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002784

₱1,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,449,186.44

Progress

Reported complete (DPWH)

Start Date

February 15, 2022

Target End

October 14, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.