Construction of Flood Mitigation Structure22KE0038

Construction of River Control along Alangilan Box Culvert, K31 + 000.00 - K31 + 120.00, K31+340 - K31+569.00, Sagay, Camiguin

Construction of River Control along Alangilan Box Culvert, K31 + 000.00 - K31 + 120.00, K31+340 - K31+569.00, Sagay, Camiguin is a DPWH-tracked public work in SAGAY (CAMIGUIN), CAMIGUIN, Region X. Reported contract value: ₱43,224,902.92. Status: Reported complete (DPWH). Contractor on record: SHEEN-SHEEN CONST CORP FORMERLY: SHEEN-SHEEN CONST. Figures trace to sumbong.

SAGAY (CAMIGUIN), CAMIGUIN, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 78%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project along Cagayan River Basin Brgy. Centro 9 to Brgy. Punta River Control, Aparri, Cagayan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002934

₱165,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001639

₱5,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003062

₱5,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱43,224,902.92

Progress

Reported complete (DPWH)

Start Date

May 21, 2022

Target End

November 13, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.