Flood Control and Drainage20PJ0008

CONSTRUCTION/ MAINTENANCE OF FLOOD CONTROL MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CALIMAG FLOOD CONTROL, CALIMAG, ALFONSO LISTA, IFUGAO

CONSTRUCTION/ MAINTENANCE OF FLOOD CONTROL MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CALIMAG FLOOD CONTROL, CALIMAG, ALFONSO LISTA, IFUGAO is a DPWH-tracked public work in Ifugao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱9,799,693.89. Status: Reported complete (DPWH). Contractor on record: JBRACHS CONST CORP. Figures trace to dpwh.

Ifugao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

12 projects · ₱58.8M total · 0 flags

Other projects by this contractor

No sat.

DESIGN AND CONSTRUCTION OF EYE - EAR DIAGNOSTIC AND LABORATORY BUILDING CUM EQUIPMENT IN THE IFSU EYE CENTER - IFUGAO STATE UNIVERSITY, ALFONSO LISTA, IFUGAO

Cordillera Administrative Region, Cordillera Administrative Region

2024₱9.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - AMGANAD - POITAN - ROAD LEADING TO POITAN RICE TERRACES, BRGYS AMGANAD & POITAN, BANAUE, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2020₱9.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION /IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - ACCESS ROAD LEADING TO MUN-ALAJA WATERFALLS, BRGY. LIWO, MAYOYAO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2020₱9.8M
Reported complete (DPWH)
No sat.

LOCAL INFRASTRUCTURE PROGRAM- RESTORATION OF THE HERITAGE AND SPANISH TRAILS FOR HORSEBACK RIDING SITE IN THE MUNICIPALITY OF MAYOYAO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2019₱4.9M
Reported complete (DPWH)
No sat.

LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF ROADS, MONGOL- TALBOC, MAYOYAO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2020₱2.9M
Reported complete (DPWH)
No sat.

25PJ0048-CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LITTLE TADIAN, ALFONSO LISTA, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2025₱2.0M
Reported complete (DPWH)
View all 12 projects →

4. Implementation

Contract Amount

₱9,799,693.89

Progress

Reported complete (DPWH)

Start Date

March 16, 2020

Target End

October 5, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.