DPWH transparency mirror

DPWH reports: Completed · 100%

Open DPWH portal record ↗

Publicly reported (according to cited sources)

  • Commission on Audit (fraud audit report to ICI) · 2026-01-20

    “no structure at the approved site and determined that the structure identified by DPWH existed nearly a year before the contract took effect”
    Source link (external) ↗

Publicly reported by the cited sources; not a finding by this site. Criminal or administrative charges, where cited, are described as pending unless the source states a final judgment. Right of reply / submit evidence

Construction of Slope Protection Structure24CC0087

Construction of Riverbank Protection Structure at Barangay Batbatnin, Malolos City, Bulacan

Construction of Riverbank Protection Structure at Barangay Batbatnin, Malolos City, Bulacan is a DPWH-tracked public work in CITY OF MALOLOS (CAPITAL) (BULACAN), BULACAN, Region III. Reported contract value: ₱77,199,938.27. Status: Reported complete (DPWH). Contractor on record: DARCY & ANNA BUILDERS & TRADING. Figures trace to sumbong.

CITY OF MALOLOS (CAPITAL) (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Bahay Pare, Meycauayan City, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007285

₱1,480,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005755

₱1,178,933.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0017916

₱440,428.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007286

₱137,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005756

₱95,671.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱77,199,938.27

Progress

Reported complete (DPWH)

Start Date

February 7, 2024

Target End

October 3, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.